带阻塞限制的船舶分段生产流水线调度 被引量:3

Blocking flow line scheduling of panel block in shipbuilding
下载PDF
导出
摘要 针对船舶分段生产流水线中船舶分段所占空间和重量大的特点,结合流水线阻塞限制、准备时间等特点,构建了阻塞流水线调度模型。以最小化分段完工时间为目标,采用基于最小位置值的编码,将连续的布谷鸟搜索算法用于求解离散的调度问题;提出一种基于改进的随机NEH启发式规则的初始化方法改进布谷鸟搜索算法,使初始种群具有多样性,提高搜索的性能。通过算例验证了改进布谷鸟搜索算法解决带阻塞的Flow-Shop问题的有效性。结合某造船企业实际数据进行应用,结果表明该调度模型和方法在企业中能获得比当前生产流水线更好的调度方案。 For the features of large space and weight occupied by panel block in panel block production line, a bloc- king flow line scheduling model was constructed with blocking restriction. Aiming at the scheduling of panel block in shipbuilding problems with minimum makespan as objective, an improved Cuckoo Search (CS) algorithm was pro- posed. An encoding scheme based on smallest position value was applied to deal with discrete scheduling problems with successive CS algorithm. A basic CS algorithm was improved by an initialization method based on improved random NEH heuristic rule, which could help initial population with certain diversity and improve the search performance. Through an example test, the effectiveness of new algorithm was verified for solving the blocking flow- shop scheduling problem. With the data from a real shipyard, the application indicated the proposed model and method resulted in better solutions than those eurrently practiced in the company.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2016年第10期2305-2314,共10页 Computer Integrated Manufacturing Systems
关键词 阻塞 船舶分段 完工时间 布谷鸟搜索算法 blocking panel block makespan cuckoo search algorithm
  • 相关文献

参考文献14

  • 1HALL N G, SRISKANDARAJAH C. A survey of machine scheduling problems with blocking and no-wait in process[J]. Operations Research, 1996,44(3) : 510-525.
  • 2GRABOWSKI J, PEMPERA J. Sequencing of jobs in some pr- oduction system [J]. European Journal of Operational Re- search,2000,125(3) :535-550.
  • 3ABDULKADER M M S, E1BEHEIRY M M, AFIA N H, E1- KHARBOTLY A K. Scheduling and sequencing in four ma- chines robotic cell: application of genetic algorithm and enu- meration techniques[J]. Ain Shams Engineering Journal, 2013, 4(3) :465-474.
  • 4ALLAHVERDI A, NG C T, CHENG T C E, KOVALYOV M Y. A survey of scheduling problems with setup times or costs[J]. European Journal of Operational Research, 2008,187 (3) :985-1032.
  • 5RONCONI D P. A note on constructive heuristics for the flow- shop problem with blocking[J]. International Journal of Pro- duction Economics, 2004,87 (1) : 39-48.
  • 6RONCONI D P, HENRIQUES L R S. Some heuristic algo- rithms for total tardiness minimization in a flowshop with bloc- king[J]. Omega,2009,37(2) :272-281.
  • 7LIANG J J, PAN Q K, TIEJUN C, WANG L. Solving the blocking flow shop scheduling problem by a dynamic multi- swarm particle swarm optimizer[J]. The International Journal of Advanced Manufacturing Technology, 2010, 55 ( 5-8 ) : 755-762.
  • 8WANG L, PAN Q K, SUGANTHAN P N, WANG W H, WANG Y M. A novel hybrid discrete differential evolution al- gorithm for blocking flow shop scheduling problems[J]. Corn-puters & Operations Research. 2010,37 (3) : 509-520.
  • 9LEE K J, LEE J K, CHOI S Y. A spatial scheduling system and its application to ship building:DAS-CURVE[J]. Expert Systems with Application, 1996,10(3/4) : 311-324.
  • 10YANG X S, DEB S. Cuckoo search via Levy flights[C]// Proceedings of World Nature &Biologically Inspired Compu- ting India. Washington, D. C. , USA: IEEE Publications, 2009 : 210-214.

同被引文献12

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部