杨房沟水电站导流隧洞工程施工测量

Construction survey of diversion tunnel of Yangfanggou Hydropower Station
下载PDF
导出
摘要 以杨房沟水电站导流洞工程为实例,对该导流洞施工控制测量、施工放样测量、内业处理及工程量计算等施工测量技术进行了详细介绍、提出利用地面高精度控制点在洞壁上补设低一级的控制点,结合边角后方交会测量方法,应用洞内相对坐标系统开展洞内直线段测量。该测量方式在保证隧洞现场放样和断面验收精度符合要求的同时提高了工作效率,对类似水电站洞室施工测量工作具有一定参考价值。 Taking the diversion tunnel construction of Yangfanggou Hydropower Station as an example, construction survey techniques including control survey, lofting measurement, indoor work and engineering quantity calculation are introduced in detail. It is proposed that one - level lower control points could be set on the tunnel wall by using high - accuracy control points on the ground, and the measurement inside the straight tunnel was carried out by using in - tunnel relative coordinate system combined with side - angle resection measurement. The proposed measurement method ensured that the accuracy of in - situ lofting and cross - section measurement met the check acceptance requirements and at the same time improved the work efficiency, which could provide reference for construction survey of similar diversion tunnels.
出处 《人民长江》 北大核心 2016年第20期74-77,共4页 Yangtze River
关键词 导流洞 施工测量 工程计量 杨房沟水电站 diversion tunnel construction survey engineering measurement Yangfanggou Hydropower Station
  • 相关文献

参考文献2

二级参考文献7

  • 1GB50026-2007工程测量规范[S].北京:中国计划出版社,2007.
  • 2张正禄.工程测量学[M].武汉:武汉大学出版社,2010.
  • 3崔洪斌.AutoCAD实践教程[M].北京:高等教育出版社,2005.
  • 4DL/T5173-2012,水电水利工程施工测量规范[S].北京:中国电力出版社,2012.
  • 5王文胜,孙全,杜正乔.浅谈水利枢纽地下洞室群工程监理测量过程控制[J].水利学报,2011,(6):81.
  • 6杨爱明.溪洛渡地下主厂房开挖控制测量的布设及应用[C]//水利水电测绘科技论文集,长江出版社,2012.
  • 7杜正乔,付江山.数字正射影像图在SCS G2004软件中的应用[J].西北水电,2011(6):81-84. 被引量:1

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部