为了节约能源,某燃煤电厂创造性提出了大型储煤筒仓加旋转卸料机的储配煤方案,有效地解决了煤场占地面积大、扬尘污染、管理成本高和存卸煤效率低下等问题,该种"搭配"模式为国内电力系统首例。
In order to save energy,a coal- fired power plant is creatively proposed the large coal storage silos with rotary unloader storing coal blending scheme. It effectively solved the coal yard area,dust pollution,high management cost and low coal storage unloading efficiency,this kind of the large coal storage silos with rotary unloader mode is the first case of power system in China.
出处
《电力科技与环保》
2016年第5期44-46,共3页
Electric Power Technology and Environmental Protection
关键词
筒仓
卸料机
保护系统
自动控制
silo
unloader
protection system
automatic control