摘要
导管架平台与上部组决在常规上采用直接焊接的方式,针对导管架与临时钻井甲板的连接处,考虑钻井完成后临时钻井甲板需要拆除,从缩短海上施工时间,节省材料的方面考虑,提出了新型的连接方式,并采用SACS软件和ABAQUS软件对其进行了整体和局部强度的校核。
The pipe rack platform and the upper part of the block are directly welded in the conventional way. Considering the connection between the pipe rack and the temporary drilling deck, and considering the need of temporary drilling deck after the completion of drilling, the new type of connection mode is put forward, which can shorten the construction time and save material. And the SACS software and ABAQUS software were used to check the whole and local strength.
出处
《中国海洋平台》
2016年第5期40-44,共5页
China offshore Platform