基于AHP-熵值法的水利工程施工进度风险模糊综合评价 被引量:22

Fuzzy Comprehensive Evaluation of Construction Schedule Risk of Water Conservancy Project Based on AHP and Entropy Value Method
下载PDF
导出
摘要 准确评价水利工程施工阶段各个项目施工进度风险并提前做好风险预案,对顺利完成各个施工项目有重要作用。对此,本文分别采用层次分析法(AHP)和信息熵理论计算权重系数,给出了影响水利工程施工进度风险的AHP-熵权组合方法,据此得出风险因素的组合权重,并进行模糊综合评价。以南水北调中线工程渚河北支排水倒虹吸工程为例,获得了该工程的主要风险因素,提出了相应的防治措施,为工程风险防范和进度控制提了依据。 It is of great significance for the successful completion of projects to accurately carry out project construction schedule risk analysis and make risk plans in advance.In this paper,analytic hierarchy process(AHP)and information entropy theory were adopted to calculate the weight coefficients,and combination of AHP and entropy weight method was proposed to analyze water conservancy construction schedule risks.Then combined weight of risk factors was obtained and fuzzy comprehensive evaluation was performed.Taking the drainage inverted siphon project of Zhuhe River north tributary in Middle Route of South-to-North Water Diversion Project as research subject,the major risk factors were obtained and the corresponding control measures were put forward,which provides a basis for engineering risk prevention and schedule control.
出处 《水电能源科学》 北大核心 2016年第10期137-140,共4页 Water Resources and Power
关键词 层次分析法 熵值法 施工进度风险 模糊综合评价 渚河北支排水倒虹吸 Analytic hierarchy process entropy value method construction schedule risk fuzzy comprehensive evaluation drainage inverted siphon project of north tributary in Zhuhe River
  • 相关文献

参考文献5

二级参考文献16

  • 1Antill J M, Woodhead R W. Critical Path Methods in construction Practice[M]. New York: A Wiley Inter- science Publication, 1982.
  • 2Ming L, Abou Rizk S M. Simplified CPM/PERT simulation mode [J]. Journal of Construction Engineering and Management, ASCE,2000, 126(3) : 219- 226.
  • 3Badiru A B. A simulation approach to PERT network analysis[J]. Simulation, 1999,57(4) : 245-255.
  • 4张杰.大跨度桥梁施工期风险分析方法研究[D].上海:同济大学土木工程学院,2008.
  • 5Mark G S. Reliability-based assessment of ageing bridges using risk ranking and life cycle cost decision analysis[ J]. Reliability Engineering and System Safety 2001,74:263 -275.
  • 6朱瑶宏.杭州湾跨海大桥项目施工期风险分析[D].成都:西南交通大学,2002.
  • 7刘有军,胡光明等.大同市城市综合交通规划专题报告--专项规划[Z].武汉:华中科技大学,2005.
  • 8Samanta B,Roy T K.Multi-objective entropy transportation model with trapezoidal fuzzy number penalties,sources,and destinations[J].Journal of Transportation Engineering,2005,131(6):419-428.
  • 9盛骤,等.概率论与数理统计[M].北京:高等教育出版社,1997.
  • 10邱菀华.群组决策特征根法[J].应用数学和力学,1997,18(11):1027-1031. 被引量:98

共引文献49

同被引文献169

引证文献22

二级引证文献96

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部