猴子岩水电站厂房顶棚结构施工方案优化 被引量:1

Optimization of powerhouse ceiling construction scheme for Houziyan Hydropower Station
下载PDF
导出
摘要 大渡河猴子岩水电站主副厂房及安装间顶棚结构采用δ=1.6 mm及4 mm厚度的镀锌压型钢模板。论述了顶棚结构制安工作的特点和施工顺序,对比了利用厂房永久桥机平台和搭设临时钢模施工平台两种施工方案,并介绍了搭设临时钢模施工平台设计方案的优化,分析了优化后方案的经济效益和实施效果。 Houziyan Hydropower Station is located on Dadu River. The ceiling structure of its main and auxiliary powerhouse as well as erection bay is designed with galvanized pressed steel formwork of 1.6mm- or 4mm-thick. An introduction was made on the features of ceiling fabrication and erection as well as on the construction proce-dure. Two construction platform schemes were compared, one is temporary steel formwork platform and another is permanent bridge crane platform. The authors also present the optimization of temporary steel platform scheme, and analyze the economic benefits from optimization and implementation effects.
作者 张朝 刘建军
出处 《广西水利水电》 2016年第5期59-62,共4页 Guangxi Water Resources & Hydropower Engineering
关键词 顶棚结构 镀锌压型钢模板 方案优化 猴子岩水电站 Ceiling structure galvanized pressed steel formwork optimization of scheme Houziyan Hydropower Station
  • 相关文献

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部