摘要
针对D-A^2O污水处理示范工程,确定了该工程基本运行条件及参数,并以间歇运行的方式作为应对水量及碳源极度缺乏的调控策略。在确定的运行条件和参数下,以间歇运行方式为调控策略可获得高效、稳定的污染物去除效果。当水温为24℃时,系统对COD、TN、NH_3-N、TP的去除率分别为77.92%、90.55%、91.93%、62.23%;低温时系统对COD、TN、NH_3-N、TP的去除率分别为75.36%、80.12%、82.04%、51.32%。不同温度下示范工程出水COD、TN、NH_3-N、TP浓度分别为(19.12~23.07)、(0.65~1.02)、(0.34~0.68)、(0.21~0.36)mg/L,出水水质均优于一级A标准。在应对碳源极度缺乏的调控策略下,D-A^2O示范工程中污泥可保持较高活性。根据D-A^2O技术的发展沿革,分析了示范工程研究成果的适用性,据此阐明其推广应用的可能性。
The basic operation conditions and parameters of the D-A20 sewage treatment demon- stration project were determined, and the intermittent operation mode was used as a regulation strategy to cope with the insufficient sewage quantity and the extreme lack of carbon source. Under the determined operation conditions and parameters, the intermittent operation mode as the regulation strategy could obtain a more efficient and stable pollutant removal efficiency. When sewage temperature was 24℃, the removal rates of COD, TN, NH3 - N and TP were 77.92%, 90. 55%, 91.93% and 62.23%, respectively. The removal rates of COD, TN, NH3 - N and TP at low temperature were 75.36%, 80. 12%, 82.04% and 51.32%, respectively. The effluent concentrations of COD, TN, NH3 -N and TP at different temperatures were 19.12 to 23.07 rag/L, 0.65 to 1.02 mg/L, 0.34 to 0.68 mg/L and 0.21 to 0.36mg/L, respectively. The effluent quality was superior to the level A criteria specified in the national discharge standards. Under the regulation strategy for extreme lack of carbon source, the activated sludge in the D-A2O demonstration project could maintain a high activity. According to the development and evolution of D-A2O technology, the applicability of the research results of the demonstration project was analyzed, and the possibility of its application was expounded.
作者
叶长兵
周志明
马乐宽
李嘉
刘琴
李兰
YE Chang-bing ZHOU Zhi-ming MA Le-kuan LI Jia LIU Qin LI Lan(College of Resources and Environment, Yuxi Normal University, Yuxi 653100, China Yunnan Bingsen Environmental Engineering Co. Ltd., Yuxi 653100, China Department of Water Environmental Planning, Chinese Academy for Environmental Planning, Beijing 100012, China)
出处
《中国给水排水》
CAS
CSCD
北大核心
2016年第23期101-104,108,共5页
China Water & Wastewater
基金
国家自然科学基金资助项目(51568066)
云南省科技厅青年项目(2016FD114)
关键词
D—A2O
生活污水
示范工程
碳源缺乏
调控策略
D-A2O
domestic sewage
demonstration project
lack of carbon source
regulation strategy