摘要
文章介绍了八钢6m焦炉长结焦时间下的热工管理实践。通过合理编排出炉计划,加强焦炉炉体的维护,确定不同周转时间下的标准温度,采取调整炉头、横排、直行温度等加热制度措施。实现了长结焦时间较低标准温度下各项热工技术指标有保障的生产模式。
This paper mainly introduces some heating management regulations of 6m coke oven of Bayi steel under long coking time. Through the reasonable arrangement discharging plan, strengthen the coke oven furnace body maintenance,determine the standard temperature under different turnaround time, take effective measures to adjust coke end temperature, horizontal temperature, longitudinal temperature and many more heating cycle etc. The production mode of ensure all thermal technical index of coke oven have been achieved under the long coking time and low standard temperature.
出处
《新疆钢铁》
2016年第2期13-16,共4页
Xinjiang Iron and Steel
关键词
焦炉
结焦时间
加热制度
炉头温度
coke oven
coking time
heating cycle
coke end temperature