摘要
某新建高速公路在摊铺GAC-25沥青混凝土下面层路面时出现施工质量效果差的问题。通过对施工的机械配置和施工路段进行分析,对沥青路面实施效果进行分析及对路面使用效果评价,在路面出现质量问题时采取相应的控制措施并取得了良好效果。
Problem of poor effect of construction quality of GAC-25 asphalt concrete lower pavement layer appeared at a new ex- pressway project, through analysis on the mechanical configuration and construction sections, study on the effect of asphah pave- ment and evaluation for the pavement performance have been carried out, so the corresponding control measures have been taken when pavement quality problem appeared with good results being achieved.
出处
《广东公路交通》
2016年第5期26-29,43,共5页
Guangdong Highway Communications
关键词
GAC-25
沥青混凝土路面
施工质量控制
GAC-25
asphalt concrete
pavement technology
construction quality control