摘要 沈阳宝能环球金融中心项目T1塔楼为在建东北第一高楼,整个底板一次性浇筑混凝土量为3.6万m3,而且浇筑过程中能利用场地仅有单侧的2 000m2,施工过程中协调难度很大,为最快完成混凝土浇筑,项目部提前策划,编制专项施工方案。最终经过153h的连续浇筑,一次性完成3.6万m3的混凝土浇筑。施工过程中采用4组溜管,溜管管径406mm,单组溜管长73m,浇筑过程中单根溜管浇筑速度达到180m3/h,创造了新的浇筑速度纪录。 The Tower 1 of Shenyang Baoneng Global Financial Center which is in construction will be the tallest building in the northeast of China, whose entire volume of concrete is 36 000m3 , which should be poured continuously with unilateral place of 2 000m2. To accomplish the task in the shortest time, the project department plans in advance, drawing up special construction scheme. Ultimately after 153 hours of continuous pouring, 36 000m3 concrete is poured successfully. Four sets of articulated chute whose diameter is 406mm and the length is 73m are utilized. The pouring speed is up to 180m3/h, which creates a new pouring record.
出处 《施工技术》 CAS 北大核心 2016年第23期10-13,共4页 Construction Technology
关键词 高层建筑 基坑 大底板 溜管 浇筑速度 施工技术 tall buildings foundation excavation massive base plate articulated chute pouringspeed construction
  • 相关文献

同被引文献18

引证文献8

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部