摘要
结合贵石沟矿井8407工作面的具体地质条件,提出了8407综放工作面回风顺槽沿顶掘进的方式,并分析了工作面回采期间矿压显现情况。结果表明,综放工作面回风顺槽沿顶掘进能够较好地解决沿底掘进存在的问题,实现安全高效生产,具有较良好的可行性。
Combines with Guishigou mine 8407 working face specific geological condition,return airway excavating along the roof of 8407 fully mechanized top coal caving face is proposed, and the conditions of mine pressure appearance are analysed. Results show that return airway excavating along the roof of fully-mechanized top coal caving face can solve the problems better on excavating along the bottom. It can achieve safe and efficient production and has relatively favourable feasibility.
出处
《煤炭技术》
CAS
北大核心
2016年第12期84-86,共3页
Coal Technology
关键词
综放开采
沿顶掘进
顶板离层
两帮位移
底鼓
fully-mechanized top coal caving
excavating along roof
roof seperation
approach of twosides of roadway
floor heave