摘要
考虑当前社会发展对电力与供热的需求,本文通过对河南电网现状及电网调峰现状的分析,结合燃气-蒸汽联合循环热电联产项目的特点与优势,以"西气东输"工程管线沿经河南某地市为例,探讨了此类项目所涉及的主机选择及接入系统电压等级问题,并总结出河南电网建设燃气电厂的必要性。
As considering power province power grid actuality and and heat demand of the current society power grid peak regulation actuality. On development, this paper has analysed Henan the basis of analyzing the characteristics and advantages of gas and steam combined cycle heat and power unite output project, and taking example for one city in Henan province passed by the project of Natural Gas Transmission form West to East China, the article has discussed selectness for main units and voltage ranking of connecting to power system involved with gas - steam combined cycle power plant, and summarized the necessary of constructing fuel gas power plant for Henan power grid.
出处
《电气开关》
2016年第6期90-92,共3页
Electric Switchgear
关键词
燃气电厂
电网调峰
燃气-蒸汽联合循环
必要性
fuel gas power plant
power grid peak regulation
gas and steam combined cycle
necessary