±800kV灵州换流站750kV GIS安装环境条件控制方案 被引量:5

Schemes on 750kV GIS installation circumstances condition control in ±800kV Lingzhou Converter Station
下载PDF
导出
摘要 针对±800 k V灵州换流站工程750 k V气体绝缘金属封闭开关(gas insulated switchgear,GIS)设备安装施工环境条件恶劣问题,通过分析工程现场实际情况,提出了设备安装环境条件控制方案。应用结果表明:设备安装环境控制方案保证了灵州换流站750 kV GIS安装条件要求,对环境变化复杂地区的超长GIS设备安装施工具有很好的示范和借鉴作用。 Aiming at the hostile condition of installation and construction for 750 kV gas insulated switchgear(GIS) in + 800 kV Lingzhou converter station project, by analyzing the practical situation of the worksite, puts forward condition control scheme. The application result shows that installation condition control scheme ensures the installation demands for 750 kV GIS in Lingzhou Converter Station, has demonstration and reference value for installation and construction of overlong GIS in complicated environmental area.
作者 段泽辰 冯昆仑 刘锐 李鲁鑫 DUAN Zechen FEN Kunlun LIU Rui LI Luxin(Power Transmission & Transformation Engineering Filiale of State Grid Ningxia Power Co, Yinehuan Ningxia 750001, China)
出处 《宁夏电力》 2016年第5期26-30,共5页 Ningxia Electric Power
关键词 特高压换流站 GIS 粉尘度 五级防尘 安装环境条件管控 UHV converter station GIS dust concentration five-level dust-proof step installation condition management and control
  • 相关文献

同被引文献21

引证文献5

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部