摘要
介绍层次分析法原理,并将其用于嵌岩灌注桩施工风险分析。运用几何平均法进行权重计算,建立嵌岩灌注桩风险评价理论体系。以重庆市云阳汽车客运中心嵌岩灌注桩施工风险为实例,对施工过程中的风险因素进行权重排序。
This paper introduces the principle of AHP (analytic hierarchy process) and applies it in risk analysis of the construction of cast - in - situ rock - socketed piles. The geometric average method is adopted to calculate the weight first, and establish the risk assessment theory system of cast -in -situ rock -socketed pile. Guided by the construction of science and technology project in Chongqing, and we take the construction risk of embedded pile in Yunyang transportation hub project as an example to weigh the risk factors in the construction process.
出处
《重庆科技学院学报(自然科学版)》
CAS
2016年第6期116-119,共4页
Journal of Chongqing University of Science and Technology:Natural Sciences Edition
基金
重庆市建设科技计划项目"大直径嵌岩灌注桩施工风险评价与控制技术研究"(城科字2014第03-3号)
关键词
层次分析法
风险因素
嵌岩灌注桩
AHP
risk factor
cast - in - situ rock - socketed piles