循环水系统运行中存在的问题及改造措施

Problems in Operation of Circulating Water System and Renovation Measures
下载PDF
导出
摘要 由于循环水系统运行不稳定,造成尿素装置蒸发系统真空度达不到工艺指标要求、蒸发表冷器封头垫片大量损坏、流量计中节流小孔经常被堵塞,严重影响了尿素装置的稳定运行和产品质量。针对存在的问题采取了一系列整改措施,尿素装置再未出现因循环水问题而导致高压系统减量运行、低压系统超压、蒸发系统停车的事故。 Because of unstable operation of circulating water system, vacuum degree of evaporation system of urea unit does not meet the requirement of technology index, cooler head gasket of evaporimeter is damaged in large number, and throttle orifice of flowmeter is blocked very often, seriously affecting the stable operation of urea unit and quality of product. In connection with existing problems, a series countermeasures are taken, ever since no accident of urea unit caused by circulating water problem appears again such as high pressure system to run in capacity reduction condition, excess pressure occurred in low pressure system, evaporation system shutdown.
出处 《化肥工业》 CAS 2016年第6期34-35,共2页 Chemical Fertilizer Industry
关键词 尿素 循环水 改造措施 urea circulating water renovation measure
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部