尾矿坝渗流是尾矿坝设计和生产管理经常遇到的问题。通过对弓长岭选矿厂尾矿库排渗治理方式的介绍,分析排渗治理前后坝体浸润线的变化,为今后的排渗设计提供参考。
Seepage of tailing dam is common problem in tailing dam design and production management. Through the introduction of eliminating seepage treatment for tailing dam of Gongchangling beneficiation plant, the paper analyzes the changes of seepage line of dam body before and after eliminating seepage treatment, providing reference for the future eliminating seepage design.
出处
《矿业工程》
CAS
2016年第6期23-25,共3页
Mining Engineering
关键词
排渗治理
坝体稳定
新型排渗技术
eliminating seepage treatment
stabilization of dam body
new type eliminating seepage technology