摘要
针对在运换流站阀厅空调系统设计存在问题进行分析,提出改进方案。通过对系统优化前后运行一个周期的空气过滤器进行性能检测检验改进方案优化后的实际效果。检测结果表明优化方案可行,达到节能降耗,降低设备运行风险的目的。
The problems in air conditioning system design of converter station valve hall were analyzed in this study, and put forward the improvement scheme. The actual effect of the improved scheme was tested through performance inspection of an air filter running a cycle before and after optimization. Test results showed that the optimized scheme was feasible, and it could achieve the purpose of saving energy and reducing the risk of equipment operation.
作者
徐辉
张斌
赵欣洋
孙力学
郝洪亮
XU Hui ZHANG Bin ZHAO Xin-yang SUN Li-xue HAO Hong-liang(State Grid Corporation of China, Yinchuan 750002,China Guodian Science and Technology Research Institute, Nanjing 210031,China)
出处
《过滤与分离》
CAS
2016年第4期6-8,共3页
Journal of Filtration & Separation
基金
国家电网公司科技项目(5229CG160001)
关键词
换流站
空调系统
阀厅
空气过滤器
converter station
air conditioning system
valve hall
air filter