摘要
通过对新建2.60 Mt/a催化裂化装置运行参数的分析计算,查找装置运行中存在的不足之处,并进行优化调整,提高装置运行的经济性。
Deficiencies existing in the running of the new built 2. 6 Mt/a FCC unit were found by analysis on operation parameters, and running economy of the unit was raised by optimization and adjustment on the parameters.
作者
邱少荣
倪维起
潘欣媚
Ni Weiqi Pan Xinmei(Shengli Refinery of Qilu Branch Co. , SINOPEC, Zibo Shandong 25543)
出处
《齐鲁石油化工》
2016年第4期270-275,共6页
Qilu Petrochemical Technology
关键词
催化装置
模拟计算
参数优化
效果
FCC unit
simulation and calculation
parameter optimization
effectiveness