低标高桩顶水下钻孔灌注桩混凝土超灌高度控制装置研制 被引量:12

Development of Control Device of Concreting in Excess for Bored Pile Underwater with Low Elevation Pile Head
下载PDF
导出
摘要 在低标高桩顶水下钻孔灌注桩施工中,用测绳人工测定混凝土超灌高度误差大,易造成桩顶混凝土欠灌或超灌高度过大等问题。根据钻孔灌注桩泥浆重度与混凝土重度不同而在一定深度下产生压力差的原理,研制了一种钻孔灌注桩混凝土超灌高度控制装置,并进行了现场试验。试验结果表明,该装置精度高,简便实用,具有较高的推广价值。 In construction of bored pile underwater with low elevation pile head,the height of concreting in excess measured with a rope has large error and easy cause under concreting or concreting in excess too much. According to the principle of pressure difference between mud and concrete,in certain depth,which was caused by the difference between bored pile mud unit weight and concrete unit weight,a control device of concreting in excess for bored pile has been developed and tested on the spot. The test results show that the device has the advantages of high precision,simple and practical,and high popularizing value.
出处 《施工技术》 CAS 北大核心 2017年第1期36-38,共3页 Construction Technology
基金 中国冶金地质总局山东局青年科技基金资助项目:黏性土地层旋挖成孔混凝土灌注桩超灌高度控制装置(2014-2015年度)
关键词 钻孔灌注桩 混凝土 超灌高度 压力差 控制装置 piles bored pile concrete height of grouting excess pressure difference control device
  • 相关文献

参考文献2

共引文献7

同被引文献51

引证文献12

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部