摘要
以太原武宿机场高架快速路工程为例,分析了钢箱梁悬空搭接施工的难度,给出了其施工工艺流程,并针对影响钢箱梁悬空搭接工程质量与工期的因素,阐述了现场施工控制方案,取得了预期的施工效果。
Taking the elevated expressway engineering of Taiyuan Wusu Airport as an example,this paper analyzed the difficulty of steel box girder hung lapping construction,gave its construction process,and according to the factors influence of the steel box girder hung lapping engineering quality and construction period,elaborated the site construction control scheme,achieved expected construction effect.
出处
《山西建筑》
2016年第35期169-170,共2页
Shanxi Architecture
关键词
钢箱梁
快速路
搭接施工
现场焊接
steel box girder
expressway
lapping construction
site welding