随机工期下反应性多模式项目调度优化 被引量:15

Reactive Strategies in the Multi-Mode Project Scheduling with Stochastic Activity Durations
下载PDF
导出
摘要 在活动工期随机中断下,通过衡量成本、鲁棒性及完工时间3类目标和两种资源分配的不同组合下,获得的反应性策略对项目调度过程中损失成本、完工时间及中断次数等方面的影响,以确定不同情况下的最优调度策略。首先对该问题进行界定,并构建问题的优化模型;设计遗传禁忌混合搜索启发式算法对模型进行求解并得出结论:遗传禁忌混合算法要优于单纯的遗传或禁忌算法;采用基于成本目标的策略可以显著降低项目反应性调度成本;在不确定度较低的环境下,传统的进度生成方式要优于随机进度生成方式。 A combination of three objectives, namely cost, robustness and project makespan, and the two kinds of resource allocation are investigated to generate six different reactive strategies. The objective is to obtain the best suitable strategy via the evaluation of adjustment cost, project makespan and the number of interruptions in the project execution process. The problem is identified first and the optimization model is constructed accordingly. Due to NP-hardness of the problem, a hybrid genetic-tabu search heuristic algorithm is developed. The proposed hybrid search heuristic outperforms the purely genetic and tabu search, and the reactive strategy based on cost minimum brings the best performance in project cost and other indexes. In low uncertain environment, the traditional schedule generation scheme is better than random schedule generation scheme.
出处 《系统管理学报》 CSSCI CSCD 北大核心 2017年第1期85-93,共9页 Journal of Systems & Management
基金 国家自然科学基金资助项目(71371150 71572138 71390331) 新世纪优秀人才支持计划资助项目(NCET-13-0460)
关键词 反应性项目调度 多模式 遗传禁忌混合算法 随机工期 reactive project scheduling multi-mode genetic-tabu hybrid algorithm stochastic durations
  • 相关文献

参考文献3

二级参考文献57

  • 1曹杰,杨晓光,汪寿阳.突发公共事件应急管理研究中的重要科学问题[J].公共管理学报,2007,4(2):84-93. 被引量:104
  • 2中国石油天然气集团公司工程技术与市场部,石油工程技术承包商协会.井喷事故案例汇编[M].北京:石油工业出版社,2006:4-190.
  • 3Herroelen W, Leus R. The construction of stable project baseline schedules[ J]. European Journal of Operational Research, 2004, 156(3) : 550-565.
  • 4Lambrechts O, Demeulemeester E, Herroelen W. A tabu search procedure for developing robusl predictive pro ieet schedule [ J]. International Journal of Production Economics, 2008, 111 (2) : 493-508.
  • 5Vonder S V D, Demeulemeester E, Herroelen W. Proactive heuristic procedures for robust project scheduling: an experimental analysis[ J ]. European Journal of Operational Research, 2008, 189 ( 3 ) : 723-733.
  • 6Yonder S V D, Ballestin F, Demeulemeester E, Herroelen W. Heuristic procedures for reactive project scheduling[ J]. Com- puters & Industrial Engineering, 2007, 52 ( 1 ) : 11-28.
  • 7Deblaere F, Demeulemeester E, Herroelen W. Reactive project scheduling in the multi -mode RCPSP[ J]. Computers & Op- erations Research, 2011, 38 ( 1 ) : 63-74.
  • 8Elmaghraby S. Activity nets: a guided tour through some recent developments[ J]. European Journal of Operational Re- search, 1995, 82(3): 383-408.
  • 9Blazewicz J, Lenstra J K, Rinnooy K A H G. Scheduling subject to resource constraints: classification and complexity[J]. Discrete Applied Mathematics, 1983, 5 ( 1 ) : 11-24.
  • 10Mika M, Waligora G, Weglarz J. Simulated annealing and tabu search for multi - mode resource-constrained project schedu- ling with positive discounted cash flows and different payment models[ J]. European Journal of Operational Research, 2005, 164(3) : 639-668.