摘要
针对来水不确定性引起的实际调度要求与原定发电计划的偏差问题,一方面结合风险管理内涵和梯级水电站发电调度操作规程,建立了梯级水电站安全运行预警机制,对发电计划进行滚动监测与评估;另一方面,基于误差分析技术和水库调度理论,建立了梯级水电站负荷调整耦合模型,并以预警结果为时间控制节点,构建二者的嵌套应用模式,同时提出了一种计及电网安全约束的负荷调整逐层递进求解算法。以雅砻江流域锦官电源组梯级水电站为实例进行计算,结果表明,所建模型可有效解决来水不确定性(偏小或偏大)导致的电站被迫降低出力运行或水库弃水问题,制定的负荷调整方案满足电网安全稳定运行约束和水电站水库运行要求,验证了所建模型的合理性。
To solve the deviation caused by inflow uncertainty between the actual operation requirements ofcascade hydropower stations and its original power generation schedule,on the one hand,an early warningmechanism for safe operation, which combines risk management connotation and hydropower stations opera-tion rules,is proposed to meet the goal of establishing continuous monitoring and evaluation on the sched-ule. On the other hand,a new coupling model of load adjustment for cascade hydropower stations is devel-oped based on error analysis method and reservoir operation theory. By setting the early warning results astime control nodes,a nested application mode for the mechanism and the model is constructed. Meanwhile,an algorithm considering security constraints in the power grid is introduced herein. Consider Jinping-guandicascade hydropower stations as an example. The modeling results show that the proposed model can effec-tively solve the problem that the power plant is forced to reduce output or release surplus water due to in-flow uncertainty. The developed load adjustment scheme can also meet the requirements of hydropower sta-tions operation and ensure safety and stability of power grids. Hence, the rationality of the model is veri-fied by the modeling results.
作者
纪昌明
李荣波
田开华
张验科
李传刚
JI Changming LI Rongbo TIAN Kaihua ZHANG Yanke LI Chuangang(School of Renewable Energy, North China Electric Power University, Beijing 102206, China Yalong River Hydropower Development Company Ltd., Chengdu 610051, China)
出处
《水利学报》
EI
CSCD
北大核心
2017年第1期1-12,共12页
Journal of Hydraulic Engineering
基金
国家自然科学基金项目(51279062
51509001)
"十三五"国家重点研发计划课题(2016YFC0402208)
中央高校基本科研业务费专项资金资助项目(2016MS51
2016XS58)
中国水利水电科学研究院流域水循环模拟与调控国家重点实验室开放研究基金资助项目(IWHR-SKL-201420)
雅砻江流域水电开发有限公司资助项目(JKZX-201416-01)
关键词
梯级水电站
来水不确定性
预警机制
负荷调整
耦合模型
锦官电源组
cascade hydropower stations
inflow uncertainty
early warning mechanism
load adjustment
coupling model
Jinping-guandi cascade hydropower stations