期刊文献+

新建隧道正交下穿施工对既有隧道的影响 被引量:6

Impact of Perpendicular Undercrossing Tunneling Construction on Existing Tunnel
下载PDF
导出
摘要 为揭示新建隧道正交下穿施工对既有隧道结构安全及地表建筑物产生的影响,依托某新建地铁区间隧道工程,采用三维有限差分方法构建了新建隧道正交下穿既有隧道的三维数值计算模型,探讨了新建隧道正交下穿施工对地表沉降及既有隧道衬砌结构产生的影响,得出了地表横向、纵向沉降规律以及既有隧道衬砌结构变形、内力的变化规律。 In order to reveal the impact of the perpendicular undercrossing tunneling construction on the structural safety of the existing tunnel and surface buildings. Based on a new subway tunnel project, a three- dimensional finite difference method is used to construct the three-dimensional numerical model for the perpendicular undercrossing tunneling construction below existing tunnel. The influence of the new tunnel construction on surface settlement and tunnel lining structure is discussed to obtain crosswise and lengthways surface settlement law and the deformation and internal force change laws of existing tunnel lining structure.
作者 胥俊玮 XU Junwei(China Railway No. 5 Bureau Group First Engineering Co. , Ltd. , Changsha 410116, China)
出处 《路基工程》 2017年第1期169-173,共5页 Subgrade Engineering
关键词 新建隧道 正交下穿 地表沉降 变形 内力 数值模拟 new tunnel perpendicular undercrossing surface settlement deformation internal force numerical analysis
  • 相关文献

参考文献10

二级参考文献92

共引文献884

同被引文献62

引证文献6

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部