摘要
电铲设备的效率是影响露天生产能力的重要因素。本文以曼家寨矿区为背景,针对目前电铲效率低下与现有生产能力要求之间的矛盾,从数理统计的角度进行电铲在不同时间段内装运时间统计,分析影响其生产能力的因素,并采取改变调车方式等手段,取得良好的工程效果。
The efficiency of electric shovel equipment is an important factor affecting the production capacity of open-air,. In this paper, the factors affecting their production capacity is analyzed after the shipment time of shovel is calculatedunder in different Timefrom the perspective of mathematical statisticsfor the contradiction between the current low efficiency of shovel andthe existing production capacity requirements based on Manjiazhai mining,the measures ,such as changing the. shunting means and other means is took,which obtain good engineering results.
出处
《世界有色金属》
2017年第1期132-133,共2页
World Nonferrous Metals
关键词
电铲
生产能力
调车方式
爆破效果
Electric shovel
production capacity
shunting method
blasting effect