摘要 呼和浩特抽水蓄能电站主机设备在安装和调试期间出现过转子磁极频繁接地、转子磁极线圈开裂、上导瓦烧瓦事故、止漏环温度异常上升、机座环拉紧螺杆断裂、机座环拉紧螺杆套管内进浆、机转子上挡风板吊杆螺母及锁片松动等问题,涉及到主机设备的设计、制造和施工工艺等缺陷。经厂家、监理和施工承包商等单位技术人员现场测试、探讨分析与研究,各项问题均得到了满意的解决,为国产设备在设计、制造和安装工艺的改进提供了宝贵经验。 In the installation and commissioning of the generator units in Hohhot Pumped Storage Power Station,various accidents and problems are encountered,such as the frequent grounding of the rotor poles,cracking of the rotor pole coil,burning of the upper guiding bearing,abnormal temperature rising of the sealing ring,breaking of the stretching screws for the stay ring,which are caused by different reasons involving the design,manufacture and construction. In this paper,typical cases are analyzed and the on-site commissioning and treatment are introduced. It could be a useful reference for the future improvement of the design,manufacture and installation techniques of domestic devices in pumped storage power stations.
作者 姚亮
出处 《水电与新能源》 2017年第2期26-30,46,共6页 Hydropower and New Energy
关键词 呼蓄电站 机组安装 案例分析 处理措施 Hohhot Pumped Storage Power Station generator unit installation case analysis treatment measures
  • 相关文献

参考文献1

二级参考文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部