摘要
结合某商务用房项目的特点,从搭设技术、经济性、安全性、时间性等方面,比选出了最佳的脚手架搭设方案,并探讨了主要受力构件的选型及用量,提出了脚手架搭设施工的控制要点,取得了良好的实施效果。
Combining with the business building project features,starting from aspects of erecting technologies,economy,safety and time,the article compares and finds out optimal scaffold erection scheme,explores major stress component selection and dosage,and puts forward scaffold erection construction control points,and finally achieves great implementation effect.
出处
《山西建筑》
2017年第3期22-24,共3页
Shanxi Architecture
关键词
脚手架
转换层
主梁
楼面
scaffold
transformation layer
main beam
floor