摘要
文章对2015年7月八钢B高炉空料线停炉操作进行了总结。通过前期制定计划降料面深度,停炉时间控制,预休风时间控制,煤气回收方式,预休风时间控制等停炉方案,实现了安全、顺利、快速停炉,减少了煤气外排时间。
In this paper, the project of blow out operating of B# BF. during empty burden line in Bayi Steel are introduced with the prophase planning material surface depth, control the time of BF blowing off and BF pre-wind off, gas recovery way, and so on.The results show that BF blowing out operation is safe, smooth and fast, reducing the gas efflux time.
出处
《新疆钢铁》
2016年第3期38-40,共3页
Xinjiang Iron and Steel
关键词
空料线
温度
停炉
empty stock line
temperature
blowing out