PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC 被引量:2

PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC
原文传递
导出
摘要 The ability to accurately characterize projects novel project characteristic is developed characteristic, called project regularity, is essential to good project management. Therefore, a reflects the value accrue within a project. This expressed in terms of the newly introduced regular/irregular-indicator RI. The widely accepted management system of earned value management (EVM) forms the basis for evaluation of the new characteristic. More concretely, the influence of project regularity on EVMforecasting accuracy is assessed, and is shown to be significant for both time and cost forecasting. Moreover, this effect appears to be stronger than that of the widely used characteristic of project seriality expressed by the serial/parallel-indicator SP. Therefore, project regularity could also be useful as an input parameter for project network generators. Furthermore, the introduction of project regularity can provide project managers with a more accurate indication of the time and cost forecasting accuracy that is to be expected for a certain project and, correspondingly, of how a project should be built up in order to obtain more reliable forecasts during project control. The ability to accurately characterize projects novel project characteristic is developed characteristic, called project regularity, is essential to good project management. Therefore, a reflects the value accrue within a project. This expressed in terms of the newly introduced regular/irregular-indicator RI. The widely accepted management system of earned value management (EVM) forms the basis for evaluation of the new characteristic. More concretely, the influence of project regularity on EVMforecasting accuracy is assessed, and is shown to be significant for both time and cost forecasting. Moreover, this effect appears to be stronger than that of the widely used characteristic of project seriality expressed by the serial/parallel-indicator SP. Therefore, project regularity could also be useful as an input parameter for project network generators. Furthermore, the introduction of project regularity can provide project managers with a more accurate indication of the time and cost forecasting accuracy that is to be expected for a certain project and, correspondingly, of how a project should be built up in order to obtain more reliable forecasts during project control.
出处 《Journal of Systems Science and Systems Engineering》 SCIE EI CSCD 2017年第1期100-120,共21页 系统科学与系统工程学报(英文版)
关键词 Project management earned value management time and cost forecasting empirical database Monte Carlo simulation project control system Project management, earned value management, time and cost forecasting, empirical database, Monte Carlo simulation, project control system
  • 相关文献

参考文献1

二级参考文献44

  • 1agilemanifesto.org. (2001). Manifesto for Agile Software Development. Available via DIALOG. http ://agilemanifesto.org/.
  • 2Amram, M. & Kulatilaka, N. (1999). Real Options: Managing Strategic Investment in an Uncertain World. Harvard Business School Press, Boston, MA.
  • 3Aumann, R. & Serrano, R. (2008). An economic index of riskiness. Journal of Political Economy, 116:810-836.
  • 4Bertsimas, D. & Sim, M. (2004). The price of robustness. Operations Research, 52: 35-53.
  • 5Brgmzei, R., Ferrari, G., Fragnelli, V. & Tijs, S. (2002). Two approaches to the problem of sharing delay costs in joint projects. Annals of Operations Research, 109:359-374.
  • 6Brown, D.B. & Sim, M. (2009). Satisficing measures for analysis of risky positions. Management Science, 55:71-84.
  • 7Cai, X., Hall, N.G. & Zhang, F. (2012). Cooperation and contract design in project management. Working paper, Department of Systems Engineering and Engineering Management, Chinese University of Hong Kong.
  • 8Castro, J., Gemez, D. & Tejada, J. (2008). A polynomial rule for the problem of sharing delay costs in PERT networks. Computers & Operations Research, 35:2376-2387.
  • 9Cooper, R.G., Edgett, S.J. & Kleinschmidt, E.J. (2000). New problems, new solutions: making portfolio management more effective. Research-Technology Management, 43: 18-33.
  • 10Corbett, C. & Muthulingam, S. (2007). Adoption of voluntary environmental standards: the role of signaling and intrinsic benets in the diffusion of the LEED green building standards. Working paper, Anderson Graduate School of Management, UCLA.

共引文献7

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部