高压引水隧洞灌浆技术研究 被引量:1

Study on Grouting Technology of High Pressure Water Diversion Tunnel
下载PDF
导出
摘要 云南万家口子水电站工程高压引水隧洞最大静水头154.55m,洞身走线中间处有一断层出露。隧洞开挖过程中,在外水压力作用下,洞室围岩存在涌水和渗透破坏,部分洞段小断层及岩溶发育。针对不同围岩段和衬砌方式,合理选择灌浆工艺、灌浆参数,有效提高围岩抗劈裂强度和防渗性能,解决地质缺陷问题。 High pressure headrace tunnel of Wanjiakouzi Hydropower Station in Yunnan,which maximum stat- ic head is 154.55m,and at the center of the hole body go line where is a fault exposed.In the process of tunnel excavation which in the external water pressure,presence of water gushing and surrounding rock permeability damage,in some areas, small faults and karsts development.According to different surrounding rock and lining, choose the grouting process and grouting parameters, so as to improve the splitting strength and anti-seepage performance of the surrounding rock effectively, and solve the problem of geological defects.
作者 魏彦军 杨柳
出处 《吉林水利》 2017年第3期8-11,共4页 Jilin Water Resources
关键词 高压隧洞 回填灌浆 固结灌浆 接触灌浆 high pressure tunnel backfill grouting consolidation grouting contact grouting
  • 相关文献

参考文献3

二级参考文献3

  • 1.地基处理手册[M].北京:中国建筑出版社,1993..
  • 2王卓昆,赵鹏高,阮殿敏.粉煤灰综合利用教材[M].沈阳:辽宁科学技术出版社,1993.
  • 3编写委员会.中国锚固与注浆工程实录选[M].北京:科学出版社,1995..

共引文献23

同被引文献9

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部