杭州地铁既有线受新线近距离斜下穿影响的变形特点分析 被引量:1

Deformation Feature Analysis of the Effect of Closely Undercrossing Construction of a New Subway Line on Existing Subway Line in Hangzhou
下载PDF
导出
摘要 地铁新线近距离斜下穿既有线路属于特级环境风险工程,虽然这方面已有一定的研究,但未见结合变化的施工参数等进行隧道动态变形的具体分析文献报道。杭州地铁4号线斜下穿既有1号线时,二者最小垂直净距仅2.1m,在软土地区无地层加固条件下对施工控制的要求非常高。分析了盾构下穿施工时既有1号线随施工参数而变化的变形特点,总结了一些规律,并给出了盾构下穿既有线路施工时的一些建议。 Closely undercrossing construction of a new subway line underneath an existing line belongs to high risk engineering projects. Though some existing studies are developed,there are few detailed analyses of the site conditions and varying construction parameters related to the observed behavior. The net vertical distance between the subway line 4 and the existing subway line 1 is only 2. 1meters for the undercrossing project in Hangzhou. The undercrossing is done without any ground improvement in soft soil area,thus it is critical for the displacement control in construction. The deformation features of subway line 1 are analyzed and some conclusions are drawn,and some suggestions are given for the undercrossing construction with considerations of specific soil and construction conditions.
作者 江建洪 马健
出处 《施工技术》 CAS 北大核心 2017年第5期102-108,共7页 Construction Technology
基金 教育部留学回国人员科研启动基金项目
关键词 地铁 盾构 近距离下穿 监测 变形控制 subways shields closely undercrossing monitoring deformation control
  • 相关文献

参考文献4

二级参考文献24

共引文献70

同被引文献7

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部