南水北调工程项目群工期优化模型研究 被引量:3

Program Time Optimization Model of South-to-North Water Diversion Project
下载PDF
导出
摘要 从业主视角出发,通过对费用最低的项目群工期优化机理的分析,利用压缩关键线路上的项目或者同时压缩关键线路、非关键线路上项目的方法,分析压缩项目群工期对项目本身、关键线路、非关键线路上项目的影响,并考虑业主因项目群工期压缩而获得的收益,据此构建基于费用最低的项目群工期优化模型。结合南水北调中线京石段应急供水工程第六标项目群的工期优化,对模型进行实证分析。 Progress goal is one of the objectives of South- to- North Water Diversion Project program. How to spend the lowest cost to achieve the program' s objectives required by the contract period of the project group has become the major is- sues of large engineering decision -making. From the owner' s perspective, by analyzing the lowest cost of the project dura- tion optimization mechanism, by compressing the critical path of the project or by both compressing the critical path and non - critical items on the line, the paper analyzes the impact of the compression program duration on the project itself, the key line, and non - critical line, and considers the benefits of the owners due to compressed schedule. Accordingly optimization model is constructed based on the cost of the minimum duration of the project group, combined with the sixth bid section of South - to - North Water Diversion Jingshi emergency water supply project. Empirical analysis is made on the model. Resuits of this study can provide a reference for the owners to scientifically and reasonably carry out large - scale projects group optimization.
作者 郑传斌 丰景春 鹿倩倩 薛松 ZHENG Chuanbin FENG Jingchun LU Qianqian XUE Song(Business School, Hohai University, Nanjing 211100, China Institute of Project Management, Hohai University, Nanjing 211100, China Jiangsu Provincial Collaborative Innovation Center of World Water Valley and Water Ecological Civilization, Nanjing 211100, China Childreng Hospital of Soochow University, Suzhou 215025, China International River Research Centre, Hohai University, Nanjing 211100, China)
出处 《科技管理研究》 CSSCI 北大核心 2017年第6期217-222,共6页 Science and Technology Management Research
基金 2014年度国家社科基金重点项目"基础设施领域财政支持公私合作伙伴(PPP)机制创新"(14AZD024) 中国博士后科学基金项目"重大水利工程项目组织协同演化及治理机制研究"(2014M551498) 中央高校基本科研业务费专项资金资助项目"大型基础设施财政支持公私合作伙伴(PPP)项目决策机制研究"(2014B09014) 教育部创新团队项目"国际河流战略与情报监测研究"(IRT13062) 国家社会科学基金青年项目"市场决定性作用下PPP项目协同监管模式研究(15CJL023)
关键词 大型工程 南水北调工程 项目群 工期优化模型 large- scale projects South- to- North Water Diversion Project program time optimization model