某难处理金矿选矿厂扩能改造及实践 被引量:3

Renovation of capacity increasing for a refractory gold ore dressing plant and its practice
下载PDF
导出
摘要 为了提高某金矿选矿厂的生产能力和金回收率,对选矿厂处理能力和工艺存在的问题进行调研,确定合理的扩能改造和工艺优化方案。通过部分设备的更新换代以及磨浮工艺的优化,改造后选矿厂设备运转率由85.35%提高至95.90%,处理能力由782 t/d提高至1 715 t/d,电能消耗由39.73 k W·h/t降低至31.36 k W·h/t,磨矿细度-0.074 mm由68.91%提高至83.22%,金浮选回收率由77.41%提高至80.94%,指标较好,显著提高了金矿资源的利用率和企业的经济效益。 In order to improve the production capacity and gold recovery in a gold ore dressing plant,the paper investigated the processing capacity and problems existing in the plant and reasonable plans of technology innovation and process optimization were made. Through upgrading the equipment and optimizing the milling and flotation technology,the equipment operation rate was increased from 85. 35 % to 95. 90 %,the processing capacity was increased from782 t/d to 1 715 t/d,the power consumption decreased from 39. 73 k W·h/t to 31. 36 k W·h/t,the grinding size(-0. 074 mm) was increased from 68. 91 % to 83. 22 %,the gold flotation recovery was increased from 77. 41 % to80. 94 %. The utilization rate of gold resources and economic benefits of the company improve prominently.
出处 《黄金》 CAS 2017年第3期54-58,共5页 Gold
基金 青海省科技支撑计划项目(2015-SF-122) 青海省2016年创新平台建设专项基金(2016-GX-G02)
关键词 难处理金矿 扩能改造 工艺优化 技术指标 处理量 回收率 refractory gold ore renovation of capacity increasing process optimization technical index processing capacity recovery rate
  • 相关文献

参考文献4

二级参考文献12

共引文献45

同被引文献16

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部