输水隧洞TBM开挖段围岩预留变形量确定方法 被引量:5

Determination of preset deformation for TBM excavation section surrounding rocks in water conveyance tunnel
下载PDF
导出
摘要 目前长距离输水隧洞预留变形量的取值一般根据工程经验及类比方法进行设置,该方法缺乏理论依据,极易造成资源浪费。根据长距离深埋隧洞的开挖支护过程及变形规律,以新疆某输水隧洞工程为依托,采用经验公式法及数值模拟法综合确定预留变形量,对同类型的工程有一定的参考价值。 The value of long distance water conveyance tunnel preset deformation is based on the engineering experience and analogy method. This method is lack of theoretical basis and easy to cause the waste of resources. According to the excavation supporting process and deformation regularity of long distance deep buried tunnel, based on a water conveyance tunnel project in Xinjiang, the experience formula method and numerical simulation method is adopted to define the preset deformation, it have a reference for the similar project.
作者 王小军 WANG Xiao-jun(Xinjiang Scientific Research Institute of Water Resources and Hydropower, Urumqi 830000, Chin)
出处 《水科学与工程技术》 2017年第1期67-69,共3页 Water Sciences and Engineering Technology
关键词 长距离隧洞 预留变形 有限元 long distance tunnel preset deformation finite element
  • 相关文献

参考文献2

二级参考文献17

共引文献76

同被引文献55

引证文献5

二级引证文献51

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部