摘要 以唐渠沟煤矿房柱式采空区下综采工作面顶板管理为背景,利用泄压爆破技术处理房采区集中煤柱,针对爆破对象不同设计了不同的爆破方案并现场进行了实施,结果表明,爆破后地表产生大量超前裂隙,位于煤柱及顶板岩层中的测点发生了不同程度的移动,现场矿压显现不明显,证明22煤煤柱在爆破后已经失稳,从而有效地避免了过煤柱期间冲击矿压灾害的发生,爆破效果显著。 In room and pillar tang conduit coal mine goaf of fully mechanized working face roof management as the background,using the pressure release blasting technology processing room mining area coal,according to different design for different blasting blasting scheme and implementation of the scene,the results show that the surface produces a large number of advanced fracture after blasting,the coal pillar and roof strata of different degrees of mobile station and the mine pressure appear is not obvious,and prove that 22 coal pillar has instability after blasting,thus effectively avoid the rock-burst disaster occurred during coal pillar,the blasting effect is remarkable.
作者 武文财
出处 《煤》 2017年第3期18-20,共3页 Coal
基金 内蒙古科技大学创新基金(31253027)
关键词 卸压爆破 集中煤柱 矿压显现 unloading blasting coal mine pressure appear
  • 相关文献

参考文献4

二级参考文献29

共引文献153

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部