高速公路项目群机械的管理与调配 被引量:1

Mechanical management and allocation of expressway programme
下载PDF
导出
摘要 为了提高高速公路项目群机械资源管理效益,基于CPM网络进度计划,根据高速公路项目群各子项目各个工序总时差以及自由时差,结合各个工序机械使用情况,采用最优规划模型,实现了各子项目的机械配备量以及项目群的机械总配备量最少。以所有机械的调运距离和为优化目标,建立调运距离优化模型,实现了项目间机械调配的总调运距离最短。研究结果表明,通过各个子项目间机械的调配,降低了机械使用高峰期机械的使用量,优化了高速公路项目群机械配备量以及机械调运距离。 To improve the efficiency of the expressway programme of mechanical resource management, based on the CPM of the network schedule, as well as the TF and the FF of every processes of each project in the expressway programme, combined with the usage of machinery in every processes of each project, the optimal planning model is used, to achieve the machine equipped with a minimum amount of each sub project, as well as the expressway programme. All the mechanical transportation distance as optimization objectives, es- tablishing the optimization model of transportation distance, to made the shortest total distance of the machinery dispatching between each sub project. The results show that through the deployment of machinery between sub projects, reducing the volume of the machinery during peak use, and realizing the optimization of expressway programme of mechanical quantity and transportation distance.
作者 刘伟军 贺圳
出处 《长沙理工大学学报(自然科学版)》 CAS 2017年第1期41-47,共7页 Journal of Changsha University of Science and Technology:Natural Science
基金 河南省交通运输厅科研项目(2013B55)
关键词 高速公路项目群 机械管理 最优规划 机械调配 距离优化 expressway programme machinery management optimal planning machinery allocation distance optimization
  • 相关文献

参考文献8

二级参考文献53

  • 1赵国杰,白玮.资源配置有效性分析的RPM方法[J].工业工程,2004,7(4):6-9. 被引量:2
  • 2赵道致,廖华,刘一骝.关键链法:一种新型的项目进度计划方法[J].天津理工大学学报,2005,21(2):8-12. 被引量:32
  • 3陈宁,章雪岩,武振业,陈石.基于随机理论的多项目资源配置模型及应用研究[J].中国管理科学,2006,14(4):75-80. 被引量:4
  • 4余建星,李彦苍.基于蚁群算法的海洋工程群项目资源调度研究[J].系统工程理论与实践,2007,27(7):57-63. 被引量:7
  • 5Michel Thiry. Combining value and project manage- ment into an effective programme management mode [J]. International Journal of Project Management, 2002,20(3) : 221-227.
  • 6Radhika Santhanam, George J Kyparisis. A decision model for interdependent information system project selection[J]. European Journal of Operational Re- search, 1996, (89) :380-399.
  • 7Chen C H, Ling S F, Chen W. Project scheduling for collaborative product development using DSM[ J]. International Journal of Project Management, 2003, (21): 291-299.
  • 8Artigues C, Michelon P, Reusser S. Insertion techniques for static and dynamic resoure-constrained project scheduling[J]. European Journal of Operational Research, 2003, 149 (2) : 249-267.
  • 9Bouleimen K, Lecocq H. A new efficient simulated annealing algorithm for resource-constrained project scheduling problem and its multiple mode version[J]. European Journal of Operational Research, 2003, 149(2) : 268-281.
  • 10Ying Y, Shou Y Y, Li M. Hybrid genetic algorithm for resource constrained multi-project scheduling problem[ J]. Journal of Zhejiang University :Engineering Science, 2009, 43 (1) : 23-27.

共引文献33

同被引文献5

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部