煤矿坚硬顶板回采巷道底鼓控制技术研究 被引量:2

Floor Heave Control of Gateroad in Hard Roof Coalmine
下载PDF
导出
摘要 针对国投塔山煤矿10209回采巷道生产地质条件,分析了回采巷道在采动影响下巷道底鼓机理及控制技术。通过分析,回采巷道底鼓主要影响因素为采动过程中的超前支承压力,建立底板岩层滑动力学模型,提出加强两帮支护强度及安装底角锚杆对底板岩层进行控制的思路。以国投塔山煤矿10217回采巷道为背景进行现场工业性试验,表明底鼓控制方案安全可靠,为坚硬顶板软岩底板回采巷道底鼓控制提供依据。 Based on geological condi t ions in No. 10209 gateroad in Tash an coa lmine, the paper makes a de ep research on the floor heave mechanism and control method under the influence of mining. By deliberate analysis,the main factors of the floor heave are the abutment pressure formed in mining, building slide mechanical model of floor strata,putting forward control ideas of strengthening the support intensity of two coal side and installing base corner bolts. Industrial experiment shows that the floor heave control method in Tashan coalmine behaved safe and reliable, it provides reference for the floor heave control in hard roof and soft floor gateroad.
作者 李忠
出处 《山西焦煤科技》 2017年第1期34-37,共4页 Shanxi Coking Coal Science & Technology
关键词 巷道底鼓 支承压力 底角锚杆 Floor heave Abutment pressure Base corner bolt
  • 相关文献

参考文献4

二级参考文献33

共引文献162

同被引文献19

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部