摘要 新景矿正加快巷道的开拓工作。为提高掘进速度,新景矿引进了太原煤科院EBJ-120TP半煤岩掘进机,在15号煤南回风大巷(东)进行快速掘进。由于原掘进出矸方式落后,为此决定利用SSJ-800皮带机出煤矸、直接接矿车运输。本课题就是对SSJ-800皮带机进行改造,解决了SSJ-800皮带机出煤矸、直接接矿车运输的难题,为快速半煤岩掘进创造有利条件。是一种较好的施工工艺。 The Xinjing coal mine is accelerating the construction of roadway.In order to increase the mining speed,Xinjing coal mine bring in the EBJ-120 TP coal-rock boring machine of Taiyuan Coal Research Institute,and driving at the east of 15th main air roadway.Because of lag in gangue transportation,therefore decide to use SSJ-800 belt conveyor to load and transported by tramcar.This thesis mainly transform the SSJ-800 belt conveyor,solve the problem of the connection between the belt conveyor and tramcar and create the favorable condition to speedy coal-rock driving,which is a kind of preferable construction technology.
作者 李剑鹏
出处 《煤矿现代化》 2017年第3期87-88,91,共3页 Coal Mine Modernization
关键词 加高 加长 接矿车 heighten lengthen connecting to tramcar
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部