摘要
在实际工作中有完成目标的时间节点,只有先行工作完成后,本工作及后续工作才能如期完成。以南京市地方海事局办公楼装修为例,逐一进行进度、质量及投资节点控制,并得控制成果为:工期节约50%;工程质量提高获评江苏省装修优质工程;投资节约4%。
There are time nodes for practical task, and following task could not be started before the previous one was finished. The Sifang Marine Bureau office building decoration project of Nanjing was taken as an example to introduce node control of construction schedule, quality and investment. The control result showed that the construction period was reduced by 50%, investment was saved by 4% and construction quality was improved, with which the project was awarded the high-quality decoration project of Jiangsu Province.
出处
《建筑技术》
北大核心
2017年第4期408-410,共3页
Architecture Technology
关键词
节点控制法
进度节点控制
质量节点控制
投资节点控制
node control method
schedule node control
quality node control
investment node control