摘要 简介地铁综合接地系统的组成,对地铁综合接地系统强弱电设备接地、接地母排、LEB箱、站外落地式导向牌接地、接地电缆的设计要求进行阐述。依据GB 50157-2013《地铁设计规范》要求,以太原地铁2号线车站为例,对地铁综合接地网的设计进行探讨,提出地铁地下车站综合接地设计方案。 The composition of the integrated grounding system of the metro line is introduced briefly and the design requirements for the grounding of strong and weak current installations, the grounding bus-bars, the LEB cabinets, the grounding of floor-type indication signs and the grounding cables of integrated grounding system of the metro line are described. According to GB 50157- 2013 Code for Design of Metro, Taiyuan Metro Line 2 is taken as an example to discuss the design of the integrated grounding grid of the metro line and a design scheme for the integrated grounding of underground stations is proposed.
作者 康晓月
出处 《建筑电气》 2017年第4期53-56,共4页 Building Electricity
关键词 综合接地系统 地铁 电阻率 强电设备 接地母排 局部等电位联结 接地电缆 变电所接地 integrated grounding system metro resistivity strong current installation grounding busbar local equipotential bonding grounding cable grounding of substation
  • 相关文献

参考文献4

二级参考文献8

共引文献22

同被引文献6

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部