摘要
随着电网建设的不断发展,越来越多的高电压大容量变电站处于兴建阶段,大截面软导线施工也越来越多,大截面软导线施工质量控制也变得越来越重要。
With the development of power grid construction, more and more transformer substations with high voltage and largecapacity are wildly being built in stages. The construction of large-section flexible conductor becomes frequent, so theconstruction quality control is becoming more and more important.
出处
《湖南电力》
2017年第A01期48-50,共3页
Hunan Electric Power
关键词
大截面软导线
飞边
散股
压接
large-section flexible conductor
flash
broken lot
crimping