摘要 针对绵阳三汇高架桥受原桥设计参数、超重超载车、支座损坏及地震等影响,第一联梁段横向偏移的问题,确立了PLC多点同步顶升系统纠偏方案,并采用钢管立柱结合承台的支撑体系,通过优化顶升纠偏技术,加强过程监控,顺利完成了梁体纠偏。 In light of the horizontal deviation problems of the first joint girder section of Sanhui viaduct in Mianyang city influenced by original bridge design parameters,over-loading and over-weight car,bearing damage and earthquake,the paper establishes PLC multi-point synchronous jacking-up system deviating scheme,and applies the bearing system by combining steel-tube vertical-column with bearing cushion. Through optimizing jacking-up deviation techniques and strengthening process monitoring,it smoothly finishes the girder deviation rectifying work.
出处 《山西建筑》 2016年第32期176-178,共3页 Shanxi Architecture
关键词 多跨连续梁 偏移量 同步顶升技术 支撑体系 multi-span continuous girder offset synchronous jacking-up technique bearing system
  • 相关文献

参考文献2

二级参考文献11

共引文献60

同被引文献12

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部