摘要
为了解决新安煤田煤层突出危险性大,煤层松软,透气性差,抽采困难的状况,提出了高压水射流石门揭煤快速消突技术。通过在孟津煤矿11031运输巷揭煤工作面采用高压水射流割缝卸压增透技术,对该揭煤区域实现了高效快速瓦斯抽采,应用表明采用该技术后平均瓦斯抽采浓度提高3倍以上,平均单孔瓦斯抽采纯量提高5倍以上;采用该技术可使瓦斯抽采钻孔量缩减82%,揭煤时间缩短73%,节约了生产成本,缓解了矿井的抽、采接替矛盾。
In order to solve the problem of high coal seam outburst danger, soft coal seam, poor permeability and difficulty in ex-traction in Xin'an Coal Field, a high - pressure water - jet technology for rapid eliminating outbust of cross - cut coal was pro-posed. By using high-pressure water-jet slotting technique, the high-efficiency and rapid gas drainage is realized in this area, andthe application shows that the average gas extraction concentration is increased by 3 times, the average single-hole gas extractionvolume increased by more than 5 times; the use of the technology can reduce the gas drainage borehole 82%, uncovering coaltime reduced by 73%, saving production costs, ease the replace contradiction of mine pumping, mining.
出处
《煤矿安全》
北大核心
2017年第4期67-70,共4页
Safety in Coal Mines
关键词
新安煤田
煤与瓦斯突出
石门揭煤
高压水射流
割缝
卸压增透
Xin'an coalfield
coal and gas outburst
rock cross-cut coal uncovering
high pressure water jet
slotting
pressurerelief and permeability increase