摘要
在工作日工序写实的基础上,结合操作规程与实际情况,摸清综掘过程中各工艺工序的操作时间、操作方法,全面分析、研究工时利用的情况,找出工时损失的原因,拟定改进工时利用的措施,为有效设定工人和设备在工作日内合理的负荷量提供必要的数据。
In working process, on the basis of realism, combined with the operating rules and actual situation, comprehensive tunneling to ascertain the operation time of each technological process Operation method, comprehensive analysis and study hours using situation, find out the cause of the loss hours, use measures to improve working hours, to effectively setting load of the workers and equipment in working days is reasonable to provide necessary data.
出处
《山东煤炭科技》
2017年第5期40-42,共3页
Shandong Coal Science and Technology
关键词
综掘
写实
工序
优化
comprehensive tunneling realistic process optimization