基于变电站综合自动化调试试验系统的104规约一致性测试应用 被引量:2

Conformance Test Application of 104 Protocol Based on Substation Integrated Automation Test System
下载PDF
导出
摘要 针对新入网(改、扩建)厂站综合自动化设备的104规约一致性的检测手段缺乏的问题,依托河北省南部电网调度自动化实验室搭建的基于D5000系统的变电站综合自动化调试试验系统104规约一致性测试的环境,提出104规约一致性测试的实现方案,以新建保定110kV王盘变电站接入调试为例,分析系统104规约一致性测试方案的应用情况,认为104规约一致性测试可提高调试效率,确保四遥信息正确。 To solve the problem of the lack of detection method of 104 protocol's conformance test of the new network equip- ment, this paper builds a conformance test environment and scheme of 104 protocol, which relies on the substation integrated automation test platform based on D5000 system in Hebei South Power Grid Dispatching Automation System Laboratory,carries out the 104 protocol's conformance test during the debugging of the new Wangpan station, which greatly improve the debugging efficiency and make sure the four information is correct.Finally, introduces the application in the Dispatching Automa- tion System of Hebei South Power Grid.
出处 《河北电力技术》 2017年第2期27-29,共3页 Hebei Electric Power
关键词 D5000 调度自动化 104规约 一致性测试 D5000 dispatching automation 104 protocol conformance test
  • 相关文献

参考文献1

二级参考文献4

共引文献9

同被引文献10

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部