摘要
为了研究复杂地质条件下综采工作面旋采技术,以某矿12124综采工作面为工程背景,采用虚心旋采方法,调斜比例设计为1∶3,带式输送机进行转弯改造,进行了复杂地质条件下旋采角度为18°、旋转距离为22.608 m的工业试验。在旋采过程中对巷道和工作面矿压进行监测,旋采效果令人满意。
To study the technology of rotary mining at fully mechanized working face under complex geological conditions, taking 12124 fully mechanized working face of a mine as the engineering background, adopted virtual rotary mining method, and designed the skew ratio which was 1:3. Further, the belt conveyor was modified to turn a corner. Based on this, an industrial test was carried out under the conditions that the rotary angle was 18° and the rotary distance was 22.068 m. During the mining process, mining pressure of the roadways and working face were monitored by corresponding equipments. The result of rotary mining is very satisfactory.
作者
赵庆民
施现院
常庆粮
ZHAO Qing-min SHI Xian-yuan CHANG Qing-liang(Shandong Energy Zibo Mining Group Co., Ltd., Zibo 255120, China Shandong Provincial Research Center of Backfill Mining Engineering and Technology, Zibo 255120, China Post-doctoral Mobile Stations, Shandong Energy Zibo Mining Group Co., Ltd., Zibo 255120, China School of Mines, China University of Mining and Technology, Xuzhou 221116, China)
出处
《煤炭技术》
北大核心
2017年第5期90-93,共4页
Coal Technology
基金
泰山学者建设工程专项经费资助项目(201309)
关键词
旋转开采
矿压显现
大倾角煤层
采空区
“三软”煤层
rotary mining
strata behaviour
large inclined angle coal seam
goal
three-soft coal seam