摘要
在架桥机安装过程中地基处理是1个重要环节。论文以虎门二桥工程为例,对中间行走通道地基处理措施、运梁通道及桥下喂梁区地基处理措施、构件堆存及绕行区处理措施进行了探讨。经荷载试验证明,地基处理后承载力达到了设计要求,取得了良好的处理效果。
Is an important link in the installation process of ground treatment of bridge erecting machine. This paper takes Humen bridge project as an example,to walk between the channel foundation treatment measures,beam channel and bridge beam feeding area foundation treatment measures,component stockpiling and treatment measures are discussed around the area.Through the load test,the bearing capacity of the foundation treatment reached the design requirements,and achieved good results.
出处
《工程建设与设计》
2017年第9期102-104,共3页
Construction & Design for Engineering
关键词
架桥机安装
地基处理
荷载试验
bridging machine installation
foundation treatment
load test