摘要
本文对某抽水蓄能电站换相隔离开关A1相在发电方向合闸未到位件进行了具体分析和处理,并对暴露问题和防范措施进行了阐述,对设备过程管控和设备验收提出了要求。
For a pumped storage power plant, the commutation phase generation chopper A1 direction closing member is not in place a specific analysis and processing and exposure problems and preventive measures were elaborated. Process control equipment and apparatus for acceptance set forth requirements.
出处
《水电与抽水蓄能》
2017年第2期132-134,140,共4页
Hydropower and Pumped Storage
关键词
抽水蓄能
换相隔离开关
机构故障
未合闸
pumped storage power
commutation knife
mechanism failure
not in place