现场岩体直剪试验及室内岩块模拟试验的探讨 被引量:2

Discussion on Direct Shear Test and Indoor Rock Mass Simulation Experiment
下载PDF
导出
摘要 为满足玉龙喀什水利枢纽工程勘测设计要求,缩短现场岩体试验周期,保证试验结果的准确可靠,对现场岩体直剪试验与室内岩块模拟试验进行对比得出:野外试验周期一组约为45天左右,室内试验试验周期10天左右,室内试验与现场试验值较为接近,表明室内模拟现场原位试验是可行的,室内试验可以降低试验成本,缩短试验周期,保证试验结果的准确可靠。 In order to meet the requirements of the survey and design of the Yulong Kashi Water Conservancy Project and to shorten the test period of the rock mass in the field and ensure the accuracy and reliability of the test results, the direct shear test of the rock mass in the field is compared with the simulation test of the indoor rock block. The indoor test is feasible, and the indoor test can reduce the test cost and shorten the test period to ensure the accuracy and reliability of the test results. The indoor test can reduce the test cost and shorten the test period.
作者 白承安
出处 《陕西水利》 2017年第3期98-100,共3页 Shaanxi Water Resources
关键词 岩体直剪试验 内摩擦角 黏聚力 模拟试验 The direct shear test of rock mass internal friction angle cohension and the simulation test
  • 相关文献

同被引文献26

引证文献2

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部