综放工作面采空区密闭墙主要技术参数研究 被引量:4

Research on Main Parameters of Mined-out Area Closed Wall in Fully Mechanized Caving Face
下载PDF
导出
摘要 为解决综放工作面采空区密闭墙构筑位置与构筑厚度不合理导致的密闭墙受压易致裂、浪费材料等问题。文章采用理论分析和数值模拟的方法,对成庄矿4320综放工作面采空区密闭墙的构筑位置与构筑厚度进行研究,得出采空区密闭墙合理厚度为2 m,最佳构筑位置在距回风巷4 m处的结论。 In order to solve the problem that the mined - out area closed wall of the fully mechanized caving faceis cracked and wasted due to the unreasonable construction position and the thickness of the closed wall. In this paper, theoretical analysis and numerical simulation are used to study the construction position and thickness of the mined - out area closed wall in the4320 fully mechanized caving face. The results show that the best position is 4m far away from the intersections of contact roadway and return airway, reasonable closed wall thickness is 2 m.
作者 翟欣 袁印
出处 《煤》 2017年第6期3-5,27,共3页 Coal
关键词 采空区 密闭墙 构筑位置 合理厚度 mined - out area closed wall construction position reasonable thickness
  • 相关文献

参考文献8

二级参考文献65

共引文献199

同被引文献11

引证文献4

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部