基于有限元计算方法对新建公路隧道下穿既有水泥厂厂房施工全过程进行模拟,通过计算模拟评价新建隧道建设过程中对既有水泥厂厂房的影响范围及程度,提出保证新建隧道建设和既有水泥厂厂房运营安全的要求和措施。
Based on finite element calculation method, the simulation is made on the whole process of the construction of newly - built highway tunnel beneath existing cement plant. Through calculating the simulation evaluation of range and degree of impact on existing cement plant during the construction of newly - built tunnel, the requirements and measures of guaranteeing the construction of newly - built tunnel and operation safety of existing cement plant are put forward.
出处
《北方交通》
2017年第5期120-124,共5页
Northern Communications
关键词
新建隧道
临近下穿
数值分析
影响程度
Newly - built tunnel
Beneath adjacently
Numerical analysis
Degree of impact